Thursday, May 27, 2021

May 26 2021

    Daily Job Report


Fincon - 3 Worker's

Work on mobilizing, loading & moving material, unload 2 trucks of rebar & clean up.

 

Esp Excavation - 2 Worker's

 Work on cutting & filling grades, start digging out ponds on west & north end & clean up


           Weather - Partly Cloudy - High 75  Low 45








Wednesday, May 26, 2021

May 25 2021

   Daily Job Report


Fincon - 3 Worker's

Work on mobilizing, loading material & clean up.

 

Esp Excavation - 3 Worker's

 Work on cutting & filling grades on the west side, layout, water & compact, start digging out ponds on south end & clean up


           Weather - Cloudy & Sunny - High 75  Low 45






Monday, May 24, 2021

May 24 2021

 Daily Job Report


Fincon - 1 Worker

Layout drive approaches, bids, work on mobilizing, unload rebar for footings & floor, clean up.

 ESP Excavation - 3 Worker's
 Work on cutting & filling grades on the west building, cut from behind curb, layout, water, compact & clean up


Weather - Cloudy With Rain Early & Sunny - High 65  Low 45









Week of May 17 - 21 2021

  Daily Job Report


Fincon - 1 Worker

Work on layout, bids, start mobilizing & clean up.

ESP Excavation - 3 Worker's
 Work on cutting & filling grades on the west side, layout, water & compact, load up garbage from the site, transport equipment & clean up


           Weather - Cloudy & Sunny - High 75  Low 45



















                



December 13 2022

                                    Daily Job Report Fincon  -  4 Worker's Hang door frames in the west buildout, work on floors in east...