Thursday, July 29, 2021

July 29 2021

       Daily Job Report


Fincon - 8 Worker's

Work on the floor rebar building B, layout & clean up.

Horizon Plumbing - 2 Worker's

Work on industrial waste line & sewers on building C & clean up


              Weather - Cloudy - High 92  Low 64









Wednesday, July 28, 2021

July 28 2021

      Daily Job Report


Fincon - 8 Worker's

Work on the floor rebar building B, layout & clean up.

Horizon Plumbing - 2 Worker's

Work on industrial waste line & sewers on building C & clean up


              Weather - Sunny, Windy - High 102  Low 64









Tuesday, July 27, 2021

July 27 2021

     Daily Job Report


Fincon - 7 Worker's

Work on the floor rebar building B, layout & clean up.

 

Esp Excavation - 3 Worker's

Finish trenches for plumbers on building C, bed with pea gravel water & clean up

Horizon Plumbing - 2 Worker's

Cut and cap all pipes on building B, unload material, start on industrial waste line on building C & clean up


                   Weather - Sunny - High 99  Low 67
















July 26 2021

      Daily Job Report


Fincon - 6 Worker's

Finish setting the floor forms on building B, start on floor rebar, layout & clean up.

 

Esp Excavation - 3 Worker's

Dig trenches for plumbers on building C water & clean up

Horizon Plumbing - 2 Worker's

Work on the layout of sewer and industrial waste line building C, unload material & clean up


                   Weather - Sunny - High 101  Low 67










Monday, July 26, 2021

July 23 2021

    Daily Job Report


Fincon - 6 Worker's

Start setting the floor forms on building B, truck road base, layout & clean up.

 

Esp Excavation - 3 Worker's

Finish grading building B, compact, water & clean up

                   Weather - Sunny - High 101  Low 67







July 22 2021

    Daily Job Report


Fincon - 6 Worker's

Strip column footings on building C, layout, finish as builds on building B plumbing, truck road base for the floor on building B & clean up.

 

Esp Excavation - 3 Worker's

Work on grading building B, compact, water & clean up


                 Weather - Sunny - High 101  Low 67







Wednesday, July 21, 2021

July 21 2021

     Daily Job Report


Fincon - 6 Worker's

Pour column footings on building C, set bolts, layout, take as-builds on plumbing & clean up.

 

Esp Excavation - 3 Worker's

Transport equipment & material, finish bedding & backfilling pipework, compact, water & clean up


                 Weather - Sunny - High 98  Low 67
















Tuesday, July 20, 2021

July 19 2021

    Daily Job Report


Fincon - 4 Worker's

Work on setting up column rebar & footings on building C & clean up.

 

Esp Excavation - 3 Worker's

Transport equipment & material, start bedding & backfilling pipework, compact, water & clean up




           Weather - Partly Cloudy - High 98  Low 67









December 13 2022

                                    Daily Job Report Fincon  -  4 Worker's Hang door frames in the west buildout, work on floors in east...