Wednesday, December 29, 2021

December 29 2021

                         Daily Job Report


Fincon -  13 Worker's

Work on uncovering & covering frost & snow protection, clean snow out of panels, install lifting hardware, shoot grades and work on forming & placing rebar in bldg B footings, move & organize material, layout & clean up.

 Harris Rebar- 5 Worker's

Work on jambs & rebar for bldg C west & south side upper mat panels & clean up


 Weather - Cloudy & Snow - High 33  Low 28














Tuesday, December 28, 2021

December 28 2021


                  Daily Job Report


Fincon -  13 Worker's

Work on uncovering & covering frost & snow protection, clean snow out of panels, install lifting hardware, work forming & placing rebar in bldg B footings, move & organize material, layout & clean up.

 Harris Rebar- 6 Worker's

Work on jambs & rebar for bldg C west side upper mat panels & clean up


 Weather - Snow All Day - High 27  Low 22











December 27 2021

                         Daily Job Report


Fincon -  13 Worker's

Work on uncovering & covering frost & snow protection, clean snow out of panels, install lifting hardware, work on forming & placing rebar in bldg B footings, move & organize material, layout & clean up.



 Weather - Cloudy & Snow - High 32  Low 28















Thursday, December 23, 2021

December 23 2021

                        Daily Job Report


Fincon -  13 Worker's

Work on uncovering & covering frost & snow protection, clean snow out of panels, install lifting hardware, start forming & placing rebar in bldg B footings, move & organize material, layout & clean up.

 Harris Rebar- 2 Worker's

Work on jambs & rebar for bldg C west side upper mat panels & clean up


 Weather - Cloudy - High 50  Low 31












Wednesday, December 22, 2021

December 22 2021

                          Daily Job Report


Fincon -  13 Worker's

Work on uncovering & covering frost & snow protection, clean snow out of panels, install lifting hardware, layout bldg B footings, start forming footings & clean up.

 Harris Rebar- 4 Worker's

Work on jambs & rebar for bldg C west side upper mat panels & clean up


 Weather - Cloudy - High 39  Low 31







December 21 2021

                      Daily Job Report


Fincon - 13 Worker's

Work on uncovering & covering frost & snow protection, layout, pour 15 north & west side panels of building C, finish concrete, haul frost blankets & clean up.

 

Harris Rebar- 6 Worker's

Work on jambs & rebar for bldg C west side upper mat panels & clean up


 Weather - Sunny - High 40  Low 18









December 13 2022

                                    Daily Job Report Fincon  -  4 Worker's Hang door frames in the west buildout, work on floors in east...