Daily Job Report
Fincon - 12 Worker's
Work on exterior caulking on building C, work on overhead doors bldg C, pour & finish concrete east side of building B, install rebar in pourbacks, install bulkheads, patch floor on bldg C, layout & clean up.U.I.S Paint - 2 Worker's
Work on exterior caulking on building C, work on overhead doors bldg C, pour & finish concrete east side of building B, install rebar in pourbacks, install bulkheads, patch floor on bldg C, layout & clean up.
U.I.S Paint - 2 Worker's
Work on bldg B west wall & clean up
Work on bldg B west wall & clean up
ESP Excavation - 2 Worker's
ESP Excavation - 2 Worker's
Start on water mains, layout & clean upHighmark Elec - 2 Worker's
Start on water mains, layout & clean up
Highmark Elec - 2 Worker's
Work on conduit in pour backs building C, layout & clean up
Horizon Plumbing - 2 Worker's
Work on conduit in pour backs building C, layout & clean up
Horizon Plumbing - 2 Worker's
Work on roof drains bldg B & C, layout & clean up
Work on roof drains bldg B & C, layout & clean up