Wednesday, September 29, 2021

September 29, 2021

 Daily Job Report


Fincon - 4 Workers


Layout panels on Building C & clean up.

          Weather - Sunny with some clouds - High 57  Low 39

Tuesday, September 28, 2021

September 28, 2021

  Daily Job Report


Fincon - 6 Workers


Finish cleaning the floor of Building C, layout panels on Building C & clean up.

          Weather - Sunny with some clouds - High 68  Low 49

Monday, September 27, 2021

September 24 2021

    Daily Job Report


Fincon - 6 Workers


Finish cleaning building C floor, start the layout of panels on building C & clean up.

                  Weather - Sunny - High 83  Low 45





September 23 2021

   Daily Job Report


Fincon - 4 Workers


Work on cleaning building C floor, layout, work on ravel in panels of building B & clean up.

            Weather - Sunny - High 80  Low 45






Wednesday, September 22, 2021

September 22 2021

   Daily Job Report


Fincon - 12 Workers


Pour, finish, layout and cut the south side of building C floor and clean up.

            Weather - Sunny - High 81  Low 48
















Tuesday, September 21, 2021

September 21 2021

      Daily Job Report


Fincon - 6 Workers


Work on rebar on building C floor, layout, strip forms and remove concrete,get equipment ready for floor pour & clean up.

            Weather - Sunny - High 80  Low 45







September 20 2021

  Daily Job Report


Fincon - 6 Workers


Work on ravel in panels for Building B, layout, finish doors and chamfer and clean up.

            Weather - Sunny - High 82  Low 55







Friday, September 17, 2021

September 17 2021

     Daily Job Report


Fincon - 6 Workers


Work on rebar in building C floor, layout, strip forms and remove concrete, clean floor of Building C and clean up.

            Weather - Sunny - High 89  Low 55











September 16 2021

    Daily Job Report


Fincon - 6 Workers


Work on panels for Building B, layout, install doors and chamfer, clean floor of Building C and clean up.

            Weather - Sunny - High 87  Low 55













Wednesday, September 15, 2021

September 15 2021

  Daily Job Report


Fincon - 12 Workers


Work on installing door frames, pour, finish and cut the north side of building C and clean up.

            Weather - Sunny & Hazy - High 82  Low 58




















September 14 2021

 Daily Job Report


Fincon - 8 Workers


Work on panels for Building B, layout, install bolts for the top plate, work on the chamfer, get the equipment ready for floor pour, start installing door frames, and clean up.

            Weather - Sunny & Hazy - High 86  Low 55








December 13 2022

                                    Daily Job Report Fincon  -  4 Worker's Hang door frames in the west buildout, work on floors in east...