Monday, January 31, 2022

January 31 2022

                                       Daily Job Report


Fincon -  20 Worker's

Pour & finish remaining panels on bldg C, work on footings, strip panels, cover panels with frost blankets & clean up.

 ESP Excavation - 2 Worker's

Work on  cutting & grading footings for building C, layout & clean up



 Weather -  Sunny - High 38   Low 22

























Friday, January 28, 2022

January 28 2022

                                      Daily Job Report


Fincon -  10 Worker's

Finish up remaining panels on bldg C, epoxy rebar, install lifting hardware and brace inserts & clean up.

 Harris Rebar- 2 Worker's

Finish up bldg C remaining panels & clean up

 ESP Excavation - 2 Worker's

Work on  cutting & grading footings for building C, layout & clean up

 W.O.I. - 1 Worker

Work on  install of c channels on panels bldg B, weld & clean up


 Weather -  Sunny - High 38   Low 16
















Thursday, January 27, 2022

January 27 2022

                                     Daily Job Report


Fincon -  12 Worker's

Work on remaining panels on bldg C, epoxy rebar, install lifting hardware and brace inserts & clean up.

 Harris Rebar- 6 Worker's

Finish up jambs & rebar for bldg C remaining panels & clean up

 ESP Excavation - 2 Worker's

Work on  cutting & grading footings for building C, layout & clean up

 W.O.I. - 1 Worker

Work on  install of c channels on panels bldg B, weld & clean up


 Weather -  Sunny - High 38   Low 26









Wednesday, January 26, 2022

January 26 2022

                                    Daily Job Report


Fincon -  13 Worker's

Work on remaining panels on bldg C, epoxy rebar, clean weld plates, install lifting hardware and brace inserts, layout c channels & clean up.

 Harris Rebar- 2 Worker's

Work on jambs & rebar for bldg C remaining panels & clean up

 ESP Excavation - 2 Worker's

Work on  cutting & grading footings for building C, layout & clean up

 W.O.I. - 1 Worker

Work on  install of c channels on panels bldg B, weld & clean up


 Weather -  Sunny - High 38   Low 26
















December 13 2022

                                    Daily Job Report Fincon  -  4 Worker's Hang door frames in the west buildout, work on floors in east...