Wednesday, November 30, 2022

November 29 2022

                                                Daily Job Report


Fincon -  4 Worker's

Work on framing & backing, hang doors, move material & clean up.

Capitol Glass - 4 Worker's

Work on east building, east wall frames & clean up

Horizon Plumbing - 2 Worker's

Work on plumbing on west T.I. & clean up

Pro Heating & Air    -  2 Workers

Install duct work on east build-out, work on duct on west T.I. & east T.I., layout unload material & clean up

Canvis Drywall  -  8 Workers

Work on hanging sheetrock from north to south & unload material & clean up

Kimco - 2 Worker's

Work on fire lines in east T.I. & clean up


            Weather - Snow & Cold - High 32  Low 18































November 28 2022

                                                Daily Job Report


Fincon -  4 Worker's

Work on framing & backing, hang windows in production rooms, hang doors, move material & clean up.

Capitol Glass - 4 Worker's

Work on east building, east wall frames & clean up

UIS Paint - 1 Worker

Work on painting touchup & walls & clean up

Horizon Plumbing - 2 Worker's

Work on plumbing on west T.I. & clean up

Pro Heating & Air    -  2 Workers

Install duct work on east build-out, work on duct on west T.I. & east T.I., layout unload material & clean up

Canvis Drywall  -  8 Workers

Work on hanging sheetrock from north to south & unload material & clean up

Kimco - 2 Worker's

Work on fire lines in east T.I. & clean up


            Weather - Cloudy & Cold - High 40  Low 18

































December 13 2022

                                    Daily Job Report Fincon  -  4 Worker's Hang door frames in the west buildout, work on floors in east...