Daily Job Report
Fincon - 4 Worker's
Hang door frames in the west buildout, work on floors in east buildout, move material & clean up.
Hang door frames in the west buildout, work on floors in east buildout, move material & clean up.
Capitol Glass - 4 Worker's
Capitol Glass - 4 Worker's
Work on the doors of each building, set glass & caulking & clean up
Work on the doors of each building, set glass & caulking & clean up
Pro Heating & Air - 2 Workers
Pro Heating & Air - 2 Workers
Start on hoods in cleaning area on west T.I. finish rough in on east T.I., layout unload material & clean up
Start on hoods in cleaning area on west T.I. finish rough in on east T.I., layout unload material & clean up
ESP Excavation - 2 Workers
ESP Excavation - 2 Workers
Work on sewer lift station. & clean up
Work on sewer lift station. & clean up
Highmark Elec - 1 Worker
Highmark Elec - 1 Worker
Work on west T.I., wire up lift pumps on the sewer lift station & clean up
Work on west T.I., wire up lift pumps on the sewer lift station & clean up
Horizon Plumbing - 2 Worker's
Horizon Plumbing - 2 Worker's
Work on plumbing the water heaters & storage tanks in the east buildout & clean up
Work on plumbing the water heaters & storage tanks in the east buildout & clean up
U.I.S Paint - 1 Worker's
U.I.S Paint - 1 Worker's
Work on interior columns and c channel & clean up
Work on interior columns and c channel & clean up