Wednesday, August 31, 2022

August 31 2022

                                                      Daily Job Report


Fincon -  12 Worker's

Hang doors in East T.I., work on floors, T.I. layout handrails & start setting, finish dumpster gates & welding & clean up.

Highmark Elec - 2 Worker's

Work on bldg B & C interior power & clean up

Capitol Glass - 5 Worker's

Work on the window's in building B, layout & clean up

Horizon Plumbing -  3 worker's

Work on interior rough in on Bldg C T.I., work on gas lines in building B, start underground in West T.I. & clean up

ESP Excavation - 4  workers

Work on grading curb & gutter, work on dock paving, layout & clean up

U.I.S Paint - 2 Worker's

Work on painting bldg B blue stripe north side & clean up



            Weather - Sunny - High 98  Low 64




















Tuesday, August 30, 2022

August 30 2022

                                                     Daily Job Report


Fincon -  12 Worker's

Work on east retaining wall, work on floors, install rebar in building B, T.I. layout handrails, set dumpster gates & weld & clean up.

Highmark Elec - 2 Worker's

Work on bldg B & C interior power & clean up

Capitol Glass - 1 Worker

Work on the window's in building B, layout & clean up

Horizon Plumbing -  3 worker's

Work on interior rough in on Bldg C T.I., work on gas lines in building B & clean up

ESP Excavation - 3  workers

Work on grading curb & gutter, work on dock paving, layout & clean up



            Weather - Sunny - High 98  Low 64









August 29 2022

                                                    Daily Job Report


Fincon -  12 Worker's

Finish digging out footings & plumbing trenches for bldg B, T.I., move forms,, layout on T.I & set retaining wall footings, work on floors, layout handrails, finish pouring dock ramps & clean up.

Highmark Elec - 2 Worker's

Work on bldg B & C interior power & clean up

Capitol Glass - 2 Worker's

Work on the window's in building B, layout & clean up

Horizon Plumbing -  3 worker's

Work on interior rough in on Bldg C T.I., layout gas lines and start in building B & clean up

Arbon - 2 Worker's

Work on the dock levlers in building B, layout & clean up



            Weather - Sunny - High 95  Low 64

















Friday, August 26, 2022

August 26 2022

                                                   Daily Job Report


Fincon -  10 Worker's

Work on digging out footings & plumbing trenches for bldg B, T.I., move forms,, layout on T.I & strip east retaining wall footings, work on floors, layout handrails  & clean up.

Highmark Elec - 1 Worker

Work on bldg B & C interior power & clean up

Capitol Glass - 2 Worker's

Work on window's in building B, layout & clean up

ESP Excavation - 3  workers

Rough grade on curb & gutter, grade dock waterway, move extra dirt, layout & clean up


            Weather - Sunny - High 92  Low 64

















August 25 2022

                                                  Daily Job Report


Fincon -  14 Worker's

Pour dock paving, dig out footings & plumbing treches for bldg B T.I., move forms,, layout on T.I & pour east retaining wall footings, work on floors, layout handrails  & clean up.

Highmark Elec - 2 Worker's

Work on bldg B & C interior power & clean up

Horizon Plumbing - 2  workers

Work on interior rough in on Bldg C T.I., layout & clean up

Capitol Glass - 2 Worker's

Work on window's in building B, layout & clean up

ESP Excavation - 3  workers

Rough grade on curb & gutter, grade dock waterway, move extra dirt, layout & clean up


            Weather - Sunny - High 92  Low 64



























December 13 2022