Monday, February 28, 2022

February 28 2022

                                         Daily Job Report


Fincon -  16 Worker's

Start setting walls on building B, remove forms & reveal from the floor, straighten walls & clean up.

Weather -  Sunny - High 41   Low 22












Friday, February 25, 2022

February 25 2022

                                              Daily Job Report


Fincon -  11 Worker's

Shovel snow off panels, remove ice, get ready to lift panels & clean up.


Weather -  Windy Cold - High 26   Low 10











February 24 2022

                                             Daily Job Report


Fincon -  11 Worker's

Shovel snow off panels, remove ice, get ready to lift panels & clean up.


Weather -  Windy Cold - High 25   Low 12











Wednesday, February 23, 2022

February 23 2022

                                            Daily Job Report


Fincon -  8 Worker's

Organize material, finish installing panel shims, get ready to lift panels & clean up.

Crane Arrived..

Weather -  Windy Cold & Snow All Day- High 20   Low 17













February 22 2022

                                           Daily Job Report


Fincon -  8 Worker's

Finish install on strongbacks, organize material, install panel shims, get ready to lift panels & clean up.

Waiting On Next Available Crane...

Weather -  Windy Cold - High 32   Low 19








Monday, February 21, 2022

February 21 2022

 

Fincon -  5 Worker's

Finish strongbacks, organize material, get ready to lift panels, unload joist's for roof & clean up.

Advanced Roofing -  5 Worker's

Unload roofing material & clean up.

Waiting On Next Available Crane...

Weather -  Snow All Day - High 33   Low 25








Friday, February 18, 2022

February 18 2022

                                          Daily Job Report


Fincon -  12 Worker's

Finish braces, install strongbacks, organize material, install panel shims, get ready to lift panels & clean up.

Waiting On Next Available Crane...

Weather -  Sunny - High 42   Low 22







December 13 2022

                                    Daily Job Report Fincon  -  4 Worker's Hang door frames in the west buildout, work on floors in east...