Wednesday, April 27, 2022

April 27 2022

                                                Daily Job Report


Fincon -  12 Worker's

Work on patching building B, start patching floor on bldg B, work on weld plates, layout & work on dock extensions on bldg B, clean up.

 Wasatch  - 4 Worker's
Work on bridging & decking on Bldg c, clean up

ESP Excavation - 3 Worker's

Work on storm drain lines, layout & clean up

Highmark Elec - 4 Worker's

Work on electrical lines in pourbacks, layout & clean up

         Weather -  Partly Sunny & Windy  - High 67 Low 43





















April 26 2022

                                               Daily Job Report


Fincon -  12 Worker's

Work on patching building B, start patching floor on bldg B, work on weld plates, layout & work on dock extensions on bldg B, clean up.

 Wasatch  - 4 Worker's
Work on bridging & decking on Bldg c, clean up

ESP Excavation - 3 Worker's

Work on storm drain lines, layout & clean up

Highmark Elec - 4 Worker's

Work on electrical lines in pourbacks, layout & clean up

         Weather -  Partly Sunny & Windy  - High 64  Low 43








Tuesday, April 26, 2022

April 25 2022

                                                Daily Job Report


Fincon -  6 Worker's

Work on patching building B, work on doorways, work on dock extensions on bldg B, clean up.

 Wasatch  - 4 Worker's
Work on bridging & decking on Bldg c, clean up

         Weather -  Sunny & Windy  - High 62  Low 43
















Friday, April 22, 2022

April 22 2022

                                               Daily Job Report


Fincon -  6 Worker's

Work on patching building B, work on doorways, work on dock extensions on bldg B, clean up.

 Wasatch  - 3 Worker's
Work on bridging & decking on Bldg c, clean up

ESP Excavation - 4 Worker's

Work on storm drain box's & lines, compact, layout & clean up

         Weather -  Rain, Cloudy & Windy  - High 52  Low 38



















December 13 2022

                                    Daily Job Report Fincon  -  4 Worker's Hang door frames in the west buildout, work on floors in east...