Friday, September 30, 2022

September 30 2022

                                                   Daily Job Report


Fincon -  8 Worker's

Work on hanging man doors on building B, work on mechanical supports in the roof, move material & clean up.

ESP Excavation - 3  workers

Work on the parking lot, work on sidewalks, compact, layout & clean up

UIS Paint - 2 Worker's

Work on Bldg C East side & clean up

                   Weather - Cloudy - High 76  Low 46






Thursday, September 29, 2022

September 29 2022

                                                  Daily Job Report


Fincon -  18 Worker's

Pour & finish last four dock paving ramps & west approach, work on dock walls, work on hanging man doors on building B, work on mechanical supports in the roof, move material, cut concrete & clean up.

Horizon Plumbing -  2 worker's

Work on interior rough in on Bldg C T.I., work on gas lines in building C & clean up

ESP Excavation - 3  workers

Work on the parking lot, work on sidewalks, compact, layout & clean up

Quicksilver - 12 Worker's

Work on curb & gutter tie in's, set forms, pour & finish water way & clean up

UIS Paint - 2 Worker's

Work on Bldg C & clean up


            Weather - Cloudy - High 76  Low 46






















Wednesday, September 28, 2022

September 28 2022

                                                        Daily Job Report


Fincon -  8 Worker's

Work on dock walls, start hanging man doors on building C, work on mechanical supports in the roof, move material & clean up.

Horizon Plumbing -  2 worker's

Work on interior rough in on Bldg C T.I., work on gas lines in building C & clean up

ESP Excavation - 3  workers

Work on grading curb & gutter, work on the parking lot, work on sidewalks, compact, layout & clean up

 PRO HVAC - 2 Worker's

Work on ductwork in east building T.I. & clean up

Kimco - 2 Worker's

Work on fire sprinkler in building B & clean up

Quicksilver - 12 Worker's

Work on curb & gutter tie in's, set forms, pour & finish water way & clean up

UIS Paint - 2 Worker's

Work on Bldg C & clean up

Highmar Elec  - 1 Worker

Work on getting power in building C & clean up

            Weather - Cloudy & Rain - High 76  Low 46























September 27 2022

                                                       Daily Job Report


Fincon -  8 Worker's

Work on dock walls, start installing mechanical supports in roof, move material & clean up.

Horizon Plumbing -  2 worker's

Work on interior rough in on Bldg C T.I., work on gas lines in building C & clean up

ESP Excavation - 3  workers

Work on grading curb & gutter, work on the parking lot, work on sidewalks, compact, layout & clean up

 PRO HVAC - 2 Worker's

Work on ductwork in east building T.I. & clean up

Kimco - 2 Worker's

Work on fire sprinkler in building B & clean up

Quicksilver - 12 Worker's

Work on curb & gutter tie in's, set forms, pour & finish & clean up

UIS Paint - 2 Worker's

Work on Bldg C & clean up


            Weather - Sunny - High 76  Low 48





























December 13 2022

                                    Daily Job Report Fincon  -  4 Worker's Hang door frames in the west buildout, work on floors in east...