Thursday, October 21, 2021

October 21 2021

         Daily Job Report


Fincon - 7 Worker's

Work on wall panel forms on bldg C, rip down forms for bldg C, move material & clean up.

 

Harris Rebar- 10 Worker's

Work on 1st mat in wall panels on bldg B, move and unload rebar & clean up


        Weather - Mostly Sunny - High 67  Low 38











October 20 2021

        Daily Job Report


Fincon - 18 Worker's

Pour & install foam in 13 wall panel forms on bldg B, clean out panels, move material & organize, work on forms of bldg C panels, layout &clean up.

 

Harris Rebar- 8 Worker's

Work on 1st mat in wall panels building B & clean up


           Weather - Sunny - High 54  Low 30













Tuesday, October 19, 2021

October 19 2021

         Daily Job Report


Fincon - 7 Worker's

Work on wall panel forms on bldg C, clean out panels for the pour Bldg B, move material, inspect the west side of bldg B with city & clean up.

 

Harris Rebar- 3 Worker's

Work on chairing up1st mat in wall panels on bldg B, Unload rebar & clean up


        Weather - Cloudy with Rain  - High 47  Low 36












Monday, October 18, 2021

October 18 2021

        Daily Job Report


Fincon - 7 Worker's

Work on wall panel forms on bldg B, clean out panels for the pour, move material, inspect the west side of bldg B & clean up.

 

Harris Rebar- 12 Worker's

Work on 1st mat in wall panels on bldg B, move rebar & clean up


        Weather - Cloudy with Rain Later - High 54  Low 38











Friday, October 15, 2021

October 15 2021

       Daily Job Report


Fincon - 4 Worker's

Work on wall panel forms on bldg C, clean ou panel, move material & clean up.

 

Harris Rebar- 8 Worker's

Work on 1st mat in wall panels, unload rebar from trucks & clean up


           Weather - Cloudy - High 54  Low 30













Thursday, October 14, 2021

October 14 2021

      Daily Job Report


Fincon - 8 Worker's

Work on wall panel forms on bldg C, layout panels, move material & clean up.

 

Harris Rebar- 8 Worker's

Work on rebar columns & start 1st mat in wall panels & clean up


           Weather - Cloudy & Rain  - High 44  Low 32










October 13 2021

      Daily Job Report


Fincon - 6 Worker's

Work on laying out panels on bldg C, work on panels on buldg B, apply bond breaker & clean up.

 

Harris Rebar- 8 Worker's

Work on rebar columns & jambs in wall panels, unload truck & clean up


           Weather - Cloudy  - High 51  Low 34









December 13 2022

                                    Daily Job Report Fincon  -  4 Worker's Hang door frames in the west buildout, work on floors in east...