Column Footings Bldg B - June 28 2021
Underground Plumbing Bldg B - July 15 2021
Column Footings Bldg C - Jul 20 2021
Floor Rebar North Side Bldg B - Aug 2 2021
Waste Line's Underground Bldg C August 5 2021
Floor Rebar South Side Bldg B - Aug 9 2021
Floor Rebar Bldg C - Sep 2 2021
Panel Rebar Face Mat Bldg B - Oct 19 2021
Panel Rebar Face Mat Bldg B - Nov 2 2021
Panel Rebar interior Mat Bldg B - Nov 8 2021
Panel Rebar interior Mat Bldg B - Nov 12 2021
Panel Rebar interior Mat Bldg B - Nov 19 2021
Remaining Panel's Rebar interior Mat Bldg B - Dec 1 2021
Panel Rebar Exterior Mat Bldg C - Dec 1 2021
Panel Rebar Exterior Mat Bldg C - Dec 7 2021
Panel Rebar Exterior & Interior Mat's Bldg C - Dec 20 2021
Panel Rebar Exterior Mat Bldg C - Dec 29 2021
West & North Exterior Footings Bldg B - Dec 29 2021
East wall panels top pour Bldg C - Jan 7 2022
East & North wall panels top pour Bldg C - Jan 13 2022
South & East Exterior Footings Bldg B - Jan 12 2022
Center wall panels Bldg C - Jan 19 2022
Center wall panels Bldg C - Jan 24 2022
South & East Footing on Bldg C - Feb 3 2022
North & West Footing on Bldg C - Feb 8 2022
Dock Wall Footing's on Bldg B & C - March 22 2022
Dock Wall Footing's on Bldg B & C - March 24 2022
Dock Wall's & Footing's on Bldg B & C - April 4 2022
Pourback Rebar Bldg B - May 19 2022
Remaining Pourback Rebar Bldg B - May 25 2022

Pourback Rebar East Bldg C - June 6 2022
Final Pourback Rebar East Bldg C - June 17 2022
Spot Footing Rebar East Bldg C T.I. - June 27 2022
4 Way Bathroom & Fire Room - July 14 2022
Fire Line Flow Tests Both Buildings - July 19 2022
Sheet Rock Nailing Bathrooms Bldg B - 8/2/22
Permanent Power Bldg B - 8/25/22
Spot Footings Bldg B T.I. - 9/21/22
Power Meter set - 10-17/22
Gas Lines Bldg B - 10/17/22
Gas Lines Bldg C - 10/17/22
Fire Lines Bldg B - 10/28/22
Nutricost T.I. Bldg C - 11/21/22
No comments:
Post a Comment