City Inspections




Column Footings Bldg B - June 28  2021

Underground Plumbing Bldg B - July 15  2021

Column Footings Bldg C - Jul 20  2021




Floor Rebar North Side Bldg B - Aug 2  2021
Waste Line's Underground Bldg C  August 5 2021

Floor Rebar South Side Bldg B - Aug 9  2021

Floor Rebar Bldg C - Sep 2 2021




Panel Rebar Face Mat Bldg B - Oct 19 2021

Panel Rebar Face Mat Bldg B - Nov 2 2021
Panel Rebar interior Mat Bldg B - Nov 8 2021



Panel Rebar interior Mat Bldg B - Nov 12 2021

Panel Rebar interior Mat Bldg B - Nov 19 2021

Remaining Panel's Rebar interior Mat Bldg B - Dec 1 2021

Panel Rebar Exterior Mat Bldg C - Dec 1  2021

Panel Rebar Exterior Mat Bldg C - Dec 7  2021

Panel Rebar Exterior & Interior Mat's Bldg C - Dec 20  2021

Panel Rebar Exterior Mat Bldg C - Dec 29  2021

West & North Exterior Footings Bldg B - Dec 29  2021



East wall panels top pour Bldg C - Jan 7 2022

East & North wall panels top pour Bldg C - Jan 13 2022

South & East Exterior Footings Bldg B - Jan 12  2022

Center wall panels Bldg C - Jan 19 2022

Center wall panels Bldg C - Jan 24 2022 

South & East Footing on Bldg C - Feb 3  2022

North & West Footing on Bldg C - Feb 8  2022


Dock Wall Footing's on Bldg B & C - March 22  2022


Dock Wall Footing's on Bldg B & C - March 24  2022



Dock Wall's & Footing's on Bldg B & C - April 4  2022






Pourback Rebar Bldg B - May 19  2022













Remaining Pourback Rebar Bldg B - May 25  2022






Pourback Rebar East Bldg C - June 6  2022

Final Pourback Rebar East Bldg C - June 17  2022

Spot Footing Rebar East Bldg C T.I. - June 27  2022

4 Way Bathroom & Fire Room - July 14  2022


Fire Line Flow Tests Both Buildings - July 19  2022


  Sheet Rock Nailing Bathrooms Bldg B - 8/2/22 


Permanent Power Bldg B - 8/25/22

Spot Footings Bldg B T.I. - 9/21/22


Power Meter set - 10-17/22


Gas Lines Bldg B - 10/17/22



Gas Lines Bldg C - 10/17/22


Fire Lines Bldg B - 10/28/22

Nutricost T.I. Bldg C - 11/21/22





No comments:

Post a Comment

December 13 2022

                                    Daily Job Report Fincon  -  4 Worker's Hang door frames in the west buildout, work on floors in east...