Wednesday, December 14, 2022

December 13 2022

                                   Daily Job Report


Fincon -  4 Worker's

Hang door frames in the west buildout, work on floors in east buildout, move material & clean up.

Capitol Glass - 4 Worker's

Work on the doors of each building, set glass & caulking & clean up

Pro Heating & Air    -  2 Workers

Start on hoods in cleaning area on west T.I. finish rough in on east T.I., layout unload material & clean up

ESP Excavation - 2 Workers

Work on sewer lift station. & clean up


Highmark Elec - 1 Worker

Work on west T.I., wire up lift pumps on the sewer lift station & clean up

Horizon Plumbing - 2 Worker's

Work on plumbing the water heaters & storage tanks in the east buildout & clean up

U.I.S Paint - 1 Worker's

Work on interior columns and c channel & clean up


            Weather - Cloudy, Snow - High 34  Low 28






















December 12 2022

                                  Daily Job Report


Fincon -  4 Worker's

Finish ceiling drops in the west buildout, work on floors in east buildout, move material & clean up.

Capitol Glass - 4 Worker's

Work on the doors of each building, set glass & caulking & clean up

Pro Heating & Air    -  2 Workers

Work on duct on west T.I. & east T.I., layout unload material & clean up

Canvis Drywall  -  3 Workers

Finis up sheetrock & corner bead in east T.I. & load material & clean up


Highmark Elec - 1 Worker

Work on west T.I. & clean up

Horizon Plumbing - 2 Worker's

Start on plumbing the water heaters & storage tanks in the east buildout & clean up


Kimco - 2 Worker's

Work on fire lines in east T.I. & clean up

ESP Excavation - 2 Workers

Pump out sewer lift station. & clean up


            Weather - Sunny - High 36  Low 28








Monday, December 12, 2022

December 9 2022

                                       Daily Job Report


Fincon -  4 Worker's

Work on ceiling drops in the west buildout, work on floors in east buildout, move material & clean up.

Capitol Glass - 4 Worker's

Work on the east building, set glass & caulking & clean up

Pro Heating & Air    -  2 Workers

Install duct work on east build-out, work on duct on west T.I. & east T.I., layout unload material & clean up

Canvis Drywall  -  3 Workers

Finish up sheetrock edging in east T.I. & unload material & clean up


Highmark Elec - 1 Worker

Work on east T.I., work on center buildout on west building & clean up


Kimco - 2 Worker's

Work on fire lines in east T.I. & clean up


            Weather - Cloudy, Sun - High 36  Low 28























December 13 2022

                                    Daily Job Report Fincon  -  4 Worker's Hang door frames in the west buildout, work on floors in east...