Tuesday, November 30, 2021

November 30 2021

                Daily Job Report


Fincon - 10 Worker's

Strip wall panels on bldg B, work on forms, ravel, chamfer, and bond breaker east side of building C, layout & install lifters and weld plates in remaning building B panels, clean up.

 

Harris Rebar- 6 Worker's

Work on jambs and remaning panels for bldg B & clean up


      Weather - Mostly Sunny - High 53  Low 26






November 29 2021

                Daily Job Report


Fincon - 10 Worker's

Strip wall panels on bldg B, work on forms, ravel, chamfer, and bond breaker east side of building C, layout & clean up.

 

Harris Rebar- 6 Worker's

Work on finishing up panels for bldg B & clean up


      Weather - Mostly Sunny - High 53  Low 26





November 26 2021

                Daily Job Report


Fincon - 2 Worker's

Strip wall panels on bldg B & clean up.

 



      Weather - Mostly Sunny - High 53  Low 26




Wednesday, November 24, 2021

November 24 2021

               Daily Job Report


Fincon - 15 Worker's

Pour &install foam on remaning 9 panels on bldg B, work on forms, ravel, chamfer, and bond breaker west side of building C, layout & clean up.

 

Harris Rebar- 8 Worker's

Work on jambs & rebar for bldg C west side panels & clean up


      Weather - Cold & Cloudy - High 42  Low 26










Tuesday, November 23, 2021

November 23 2021

               Daily Job Report


Fincon - 10 Worker's

Strip wall panels on bldg B, work on forms, ravel, chamfer, and bond breaker east side of building C, layout & clean up.

 

Harris Rebar- 6 Worker's

Work on jambs and west panels for bldg C & clean up


      Weather - Mostly Sunny - High 53  Low 26








Monday, November 22, 2021

November 22 2021

              Daily Job Report


Fincon - 10 Worker's

Strip wall panels on bldg B, work on forms, ravel, chamfer, and bond breaker east side of building C, layout & clean up.

 

Harris Rebar- 6 Worker's

Work on jambs and west panels for bldg C & clean up


      Weather - Partly Cloudy - High 52  Low 26











Friday, November 19, 2021

November 19 2021

              Daily Job Report


Fincon - 15 Worker's

Pour & finish 13 panels on bldg B, work on forms, ravel, chamfer, and bond breaker west side of building C, layout & clean up.

 

Harris Rebar- 8 Worker's

Work on jambs & rebar for bldg C west side panels & clean up


      Weather - Cold & Cloudy - High 42  Low 26









November 18 2021

             Daily Job Report


Fincon - 12 Worker's

Strip wall panels on bldg B, work on forms, ravel, chamfer, and bond breaker east side of building C, layout & clean up.

 

Harris Rebar- 8 Worker's

Finish up the bottom mat in remaining 6 panels on bldg B, work on jambs for bldg C & clean up


      Weather - Partly Cloudy - High 52  Low 26




















December 13 2022

                                    Daily Job Report Fincon  -  4 Worker's Hang door frames in the west buildout, work on floors in east...