Tuesday, October 18, 2022

October 17 2022

                                             Daily Job Report


Fincon -  15 Worker's

Finish stucco east dumpster enclosures, set forms, pour & finish final approach on the east side, move material, clean up docks, cut concrete & clean up.

ESP Excavation - 3  workers

Work on the east parking lot, compact, layout & clean up

Capitol Glass - 2 Worker's

Work on east building, east wall frames & clean up

UIS Paint - 4 Worker's

Work on Bldg C & B walls & clean up

Highmark Electric- 1 Worker

Work on main power both building's & clean up

Horizon Plumbing -  2 worker's

Work on interior rough in on Bldg C T.I., finish gas lines & in building C, work on air lines & clean up

Industrial Doors -  1 worker

Finish up overhead doors in on Bldg C & clean up

                     Weather - Sunny - High 74  Low 42

















October 14 2022

                                                     Daily Job Report


Fincon -  15 Worker's

Stucco east dumpster enclosures, set forms, move material, clean up docks, cut concrete & clean up.

ESP Excavation - 3  workers

Work on the east parking lot, compact, layout & clean up

Capitol Glass - 2 Worker's

Work on east building, east wall frames & clean up

UIS Paint - 4 Worker's

Work on Bldg C & B walls & clean up

PRO HVAC - 2 Worker's

Work on ductwork in east building T.I., start on venting heaters in building B & clean up

Highmark Electric- 2 Worker's

Work on main power to east building & clean up


Industrial Doors -  1 worker

Work on overhead doors in on Bldg C & clean up

                     Weather - Sunny - High 74  Low 42















Thursday, October 13, 2022

October 13 2022

                                                    Daily Job Report


Fincon -  15 Worker's

Stucco east dumpster enclosures, set forms, pour & finish apprache on east side, move material, clean up docks, cut concrete & clean up.

ESP Excavation - 3  workers

Work on the east parking lot, compact, layout & clean up

Capitol Glass - 2 Worker's

Work on east building, east wall frames & clean up

UIS Paint - 4 Worker's

Work on Bldg C & B walls & clean up

Neils Concrete Cutting -  2 worker's

Cut floor in laundry room & drill 2 12 holes for dust collector in on Bldg C & clean up


PRO HVAC - 2 Worker's

Work on ductwork in east building T.I., start on venting heaters in building B & clean up

Highmark Electric- 4 Worker's

Work on main power to east building & clean up


Horizon Plumbing -  2 worker's

Work on interior rough in on Bldg C T.I., work on gas lines in building C & clean up

Industrial Doors -  1 worker

Work on overhead doors in on Bldg C & clean up

                     Weather - Sunny - High 74  Low 42












                  Weather - Sunny - High 74  Low 42


October 12 2022

                                                    Daily Job Report


Fincon -  6 Worker's

Stucco east dumpster enclosures, set forms, pour sidewalk on east building, move material, clean up docks, cut concrete & clean up.

ESP Excavation - 3  workers

Work on the west parking lot, compact, layout & clean up

Capitol Glass - 2 Worker's

Work on east building, east wall frames & clean up

UIS Paint - 4 Worker's

Work on Bldg C & B walls & clean up

PRO HVAC - 2 Worker's

Work on ductwork in east building T.I., start on venting heaters in building B & clean up

Highmark Electric- 4 Worker's

Work on main power to east building & clean up


Horizon Plumbing -  2 worker's

Work on interior rough in on Bldg C T.I., work on gas lines in building C & clean up

Industrial Doors -  1 worker

Work on overhead doors in on Bldg C & clean up


                  Weather - Sunny - High 74  Low 46









December 13 2022

                                    Daily Job Report Fincon  -  4 Worker's Hang door frames in the west buildout, work on floors in east...