Wednesday, March 30, 2022

March 29 2022

                                Daily Job Report


Fincon -  16 Worker's

Strip footings & dock walls, work on patching building B, pour 5 dock walls on bldg c, weld panel corners & lap panels, clean floors & clean up.

 Wasatch  - 4 Worker's
Work on bracing & angels, install roof frame drains & clean up



 Weather -  Cloudy & Rain  - High 58   Low 44

















March 28 2022

                                 Daily Job Report


Fincon -  17 Worker's

Pour footings & 5 dock walls on bldg c, work on patching building B, weld panel corners & lap panels, clean floors & clean up.

 Wasatch  - 4 Worker's
Work on bracing & angels, install roof frame drains & clean up



 Weather -  Cloudy  - High 48   Low 34








Friday, March 25, 2022

March 25 2022

                                Daily Job Report


Fincon -  16 Worker's

Work on footings for dock walls, work on patching building B, weld panel corners & lap panels, start dock walls on bldg c, clean floors & clean up.

 ESP Excavation - 4 Worker's

Work on sewer main east side & backfill & compact center main, layout & clean up

 Wasatch  - 4 Worker's
Work on bracing & angels, install roof frame drains & clean up



 Weather -  Sunny  - High 68   Low 34













Thursday, March 24, 2022

March 24 2022

                               Daily Job Report


Fincon -  16 Worker's

Work on footings for dock walls, work on patching building B, weld panel corners & lap panels, start dock walls on bldg c, clean floors & clean up.

 ESP Excavation - 4 Worker's

Work on sewer main & backfill & compact, layout & clean up

 Wasatch  - 4 Worker's
Work on bracing & angels, install roof frame drains & clean up



 Weather -  Sunny  - High 64   Low 34












March 23 2022

                              Daily Job Report


Fincon -  12 Worker's

Work on footings for dock walls, work on patching building B, weld panel corners & lap panels, clean floors & clean up.

 ESP Excavation - 4 Worker's

Work on sewer main & finish setting sewer lift station, layout & clean up

 Wasatch  - 4 Worker's
Finish iron on building B. work on bracing & angels, weld up remaining joists



 Weather -  Sunny  - High 56   Low 31










March 22 2022

                             Daily Job Report


Fincon -  11 Worker's

Work on footings for dock walls, work on patching building B, weld panel corners & lap panels, clean floors & clean up.

 ESP Excavation - 4 Worker's

Work on sewer main & sewer lift station, layout & clean up

 Wasatch  - 4 Worker's
Hang iron on building B north to south. work on sorting out decking, columns, and joists for roofs

All Cuts - 4 Worker's
Finish core drilling for roof drains, 20 - 8" Holes


 Weather -  Sunny, Windy  - High 46   Low 30












December 13 2022

                                    Daily Job Report Fincon  -  4 Worker's Hang door frames in the west buildout, work on floors in east...