Thursday, July 15, 2021

July 14 2021

  Daily Job Report


Fincon - 4 Worker's

Work on forms & rebar, layout footings for building C & clean up.

 

Esp Excavation - 3 Worker's

Dig column footings on building C, work on grading, compact, water & clean up

Horizon Plumbing - 2 Worker's

Finish up lines for building B, fill with water for test & clean up



           Weather - Sunny  - High 98  Low 67