Friday, August 6, 2021

Aug 4 2021

  

   Daily Job Report


Fincon - 7 Worker's

Work on cleaning the floor on first pour building B, set foam on column bolts for second pour, finish forms, layout, work on rebar & clean up.

Horizon Plumbing - 2 Worker's

work on building C, load material, fill with water on building and test, bed pipe & clean up


                   Weather - Sunny - High 94  Low 67















No comments:

Post a Comment

December 13 2022

                                    Daily Job Report Fincon  -  4 Worker's Hang door frames in the west buildout, work on floors in east...