Tuesday, August 10, 2021

August 10 2021

  Daily Job Report


Fincon - 14 Worker's

Pour south end of build B floor, chalk lines & saw cut, finish concrete, haul road base for building C floor, layout & clean up.

 

Esp Excavation - 3 Worker's

Haul in road base & start grading floor on building C, compact, water & clean up

                   Weather - Smokey - High 91  Low 67