Wednesday, September 15, 2021

September 14 2021

 Daily Job Report


Fincon - 8 Workers


Work on panels for Building B, layout, install bolts for the top plate, work on the chamfer, get the equipment ready for floor pour, start installing door frames, and clean up.

            Weather - Sunny & Hazy - High 86  Low 55








No comments:

Post a Comment

December 13 2022

                                    Daily Job Report Fincon  -  4 Worker's Hang door frames in the west buildout, work on floors in east...