Monday, November 1, 2021

October 22 - 31 2021

          Daily Job Report


Fincon - 7 Worker's

Work on wall panel forms on bldg C, rip down forms for bldg C, move material & clean up.

 

Harris Rebar- 10 Worker's

Finish up work on 1st mat in wall panels on bldg B, move and unload rebar & clean up


        Weather - Mostly Sunny & Some Rain - High 67  Low 38















No comments:

Post a Comment

December 13 2022

                                    Daily Job Report Fincon  -  4 Worker's Hang door frames in the west buildout, work on floors in east...