Wednesday, December 1, 2021

December 1 2021

                 Daily Job Report


Fincon - 8 Worker's

Work on forms, ravel, chamfer, and bond breaker east side of building C, layout & install lifters and weld plates in remaining building B panels, clean up.

 

Harris Rebar- 6 Worker's

Work on jambs and remaining panels for bldg B & work on west wall building C & clean up


     Weather - Mostly Sunny - High 53  Low 26