Friday, December 17, 2021

December 17 2021

                        Daily Job Report


Fincon -  7 Worker's

Work on uncovering & covering frost & snow protection, start installing lifting hardware, layout, organizing forms & clean up.

 Harris Rebar- 8 Worker's

Work on jambs & rebar for bldg C west side upper mat panels & clean up

ESP Excavation- 3 Worker's

Work on east side footings of building B, haul off material. move frost blankets, compact & clean up

 Weather - Snow & Cloudy - High 33  Low 13
















No comments:

Post a Comment

December 13 2022

                                    Daily Job Report Fincon  -  4 Worker's Hang door frames in the west buildout, work on floors in east...