Wednesday, January 26, 2022

January 26 2022

                                    Daily Job Report


Fincon -  13 Worker's

Work on remaining panels on bldg C, epoxy rebar, clean weld plates, install lifting hardware and brace inserts, layout c channels & clean up.

 Harris Rebar- 2 Worker's

Work on jambs & rebar for bldg C remaining panels & clean up

 ESP Excavation - 2 Worker's

Work on  cutting & grading footings for building C, layout & clean up

 W.O.I. - 1 Worker

Work on  install of c channels on panels bldg B, weld & clean up


 Weather -  Sunny - High 38   Low 26
















No comments:

Post a Comment

December 13 2022

                                    Daily Job Report Fincon  -  4 Worker's Hang door frames in the west buildout, work on floors in east...