Daily Job Report
Fincon - 13 Worker's
Work on uncovering & covering frost & snow protection, clean snow out of footings & panels, install lifting hardware, shoot grades and work on pouring and finishing north & west footings on bldg B, move & organize footing boards, layout & clean up.
Harris Rebar- 5 Worker's
Work on uncovering & covering frost & snow protection, clean snow out of footings & panels, install lifting hardware, shoot grades and work on pouring and finishing north & west footings on bldg B, move & organize footing boards, layout & clean up.
Harris Rebar- 5 Worker's
Work on jambs & rebar for bldg C east side upper mat panels & clean up
Work on jambs & rebar for bldg C east side upper mat panels & clean up