January 17 2022

                                Daily Job Report


Fincon -  14 Worker's

Work on uncovering & covering frost & snow protection, strip forms on bldg B footings, move & organize footing boards, clean off weld plates on bldg B, strip poured panels on bldg C, form remaining panels, layout panels on footings & clean up.


 Weather - Sunny - High 39   Low 25












No comments:

Post a Comment

December 13 2022

                                    Daily Job Report Fincon  -  4 Worker's Hang door frames in the west buildout, work on floors in east...