Thursday, January 20, 2022

January 19 2022

                                 Daily Job Report


Fincon -  13 Worker's

Work on remaning panels on bldg C, install rebar on building B panels, epoxy, clean weld plates, layout & clean up.

 Harris Rebar- 6 Worker's

Work on jambs & rebar for bldg C remaining panels & clean up


 Weather - Cloudy Cold - High 35   Low 26








No comments:

Post a Comment

December 13 2022