Tuesday, January 25, 2022

January 24 2022

                                   Daily Job Report


Fincon -  13 Worker's

Work on remaining four panels to pour face side on bldg C, epoxy rebar, clean weld plates, layout c chanels & clean up.

 Harris Rebar- 6 Worker's

Work on jambs & rebar for bldg C remaining panels & clean up

 W.O.I. - 3 Worker's

Work on  install of c channels on panels bldg B, layout & clean up


 Weather -  Sunny - High 38   Low 26














No comments:

Post a Comment

December 13 2022

                                    Daily Job Report Fincon  -  4 Worker's Hang door frames in the west buildout, work on floors in east...