Daily Job Report
Fincon - 12 Worker's
Work on Westr footings on bldg C, strip concrete footings east side, install & tie rebar, unload braces & start sorting, remove lifting insets & clean up.
Work on Westr footings on bldg C, strip concrete footings east side, install & tie rebar, unload braces & start sorting, remove lifting insets & clean up.
W.O.I. - 1 Worker
W.O.I. - 1 Worker
Work on sorting c channels on panels bldg C & clean up
Work on sorting c channels on panels bldg C & clean up