                                          Daily Job Report


Fincon -  12 Worker's

Work on footings for dock walls, strip panels with 2' windows, finish up grout under walls & clean up.

 ESP Excavation 4 Worker's

Work on  cutting & grading, finish dock wall footings for building B, layout & clean up

 Wasatch  1 Worker
Work on sorting out decking, columns, and joists for roofs