Wednesday, April 27, 2022

April 27 2022

                                                Daily Job Report


Fincon -  12 Worker's

Work on patching building B, start patching floor on bldg B, work on weld plates, layout & work on dock extensions on bldg B, clean up.

 Wasatch  - 4 Worker's
Work on bridging & decking on Bldg c, clean up

ESP Excavation - 3 Worker's

Work on storm drain lines, layout & clean up

Highmark Elec - 4 Worker's

Work on electrical lines in pourbacks, layout & clean up