Wednesday, April 20, 2022

April 18 2022

                                              Daily Job Report


Fincon -  8 Worker's

Work on patching building B, clean & cut floor joints on bldg B, work on weld plates, layout & clean up.

 Wasatch  - 4 Worker's
Work on bridging & misc welding on Bldg c, clean up

ESP Excavation - 4 Worker's

Work on sewer & backfill on dock area, compact, layout & clean up

Advanced Roofing - 4 Worker's

Work on moving material to roof, layout & clean up


            Weather -  Sunny  - High 62  Low 43