Daily Job Report
Fincon - 12 Worker's
Finish exterior caulking on building B, work on overhead doors bldg C, work on dock steel & forming the pits on building B, install rebar in pourbacks, finish removing braces on building C, layout & clean up.
Finish exterior caulking on building B, work on overhead doors bldg C, work on dock steel & forming the pits on building B, install rebar in pourbacks, finish removing braces on building C, layout & clean up.
Wasatch - 3 Worker'sWork on decking & misc welding on Bldg c, clean up
Wasatch - 3 Worker's
Work on decking & misc welding on Bldg c, clean up
ESP Excavation - 3 Worker's
ESP Excavation - 3 Worker's
Work on dock drains & sewer, compact, layout & clean up
Work on dock drains & sewer, compact, layout & clean up
U.I.S Paint - 2 Worker's
U.I.S Paint - 2 Worker's
Start on bldg B west wall & clean up
Start on bldg B west wall & clean up
Highmark Elec - 2 Worker's
Highmark Elec - 2 Worker's
Work on conduit in pour backs, layout & clean up
Work on conduit in pour backs, layout & clean up