Thursday, May 26, 2022

May 25 2022

                                Daily Job Report


Fincon -  12 Worker's

Work on exterior caulking on building C, work on overhead doors bldg C, pour & finish concrete east side of building B, install rebar in pourbacks, install bulkheads, patch floor on bldg C, layout & clean up.
U.I.S Paint - 2 Worker's

Work on bldg B west wall & clean up

ESP Excavation - 2 Worker's

Start on water mains, layout & clean up
Highmark Elec - 2 Worker's

Work on conduit in pour backs building C, layout & clean up

Horizon Plumbing - 2 Worker's

Work on roof drains bldg B & C, layout & clean up

            Weather -  Sunny  - High 72  Low 52












No comments:

Post a Comment

December 13 2022

                                    Daily Job Report Fincon  -  4 Worker's Hang door frames in the west buildout, work on floors in east...