Tuesday, May 3, 2022

May 3 2022

                                                  Daily Job Report


Fincon - 7 Worker's

Work on patching building B, start patching floor on bldg B, work on weld plates, layout & work on dock extensions on bldg B, clean up.

 Wasatch  - 4 Worker's
Work on decking on Bldg c, clean up

ESP Excavation - 3 Worker's

Work on storm drain lines, backfill & compact, layout & clean up

Highmark Elec - 3 Worker's

Work on electrical lines in pourbacks & exterior equipment, layout & clean up



         Weather -  Rain & Cloudy & Windy  - High 52 Low 34















No comments:

Post a Comment

December 13 2022

                                    Daily Job Report Fincon  -  4 Worker's Hang door frames in the west buildout, work on floors in east...