Friday, June 24, 2022

June 22 2022

                                 Daily Job Report


Fincon -  10 Worker's

Pour & finish remaining pourbacks on building C, work on patching interior bldg B & exterior of C, strip the dock pits on building C, layout & cut, layout & dig interior footings for buildout Bldg C & clean up.

U.I.S Paint - 3 Worker's

Work on painting bldg B exterior & columns & clean up


ESP Excavation - 4 Worker's

Finish up water lines, compact, layout & clean up


            Weather -  Sunny - High 78  Low 52







No comments:

Post a Comment

December 13 2022

                                    Daily Job Report Fincon  -  4 Worker's Hang door frames in the west buildout, work on floors in east...