Daily Job Report
Fincon - 12 Worker's
Work on patching interior bldg B & building C, clean forms, patch dumpster walls, cut concretelayout on T.I., work on drain trenches & clean up.
Work on patching interior bldg B & building C, clean forms, patch dumpster walls, cut concretelayout on T.I., work on drain trenches & clean up.
U.I.S Paint - 3 Worker's
U.I.S Paint - 3 Worker's
Work on painting bldg B interior & clean up
Work on painting bldg B interior & clean up
ESP Excavation - 3 workers
ESP Excavation - 3 workers
Rough grade on west & north ponds, grade docks, move extra dirt, layout & clean up
Rough grade on west & north ponds, grade docks, move extra dirt, layout & clean up
Industrial Door - 1 Worker
Industrial Door - 1 Worker
Work on overhead doors, load move & unload material, layout & clean up
Work on overhead doors, load move & unload material, layout & clean up
Weather - Sunny - High 102 Low 70