Friday, July 8, 2022

June 28 2022

                                     Daily Job Report


Fincon -  9 Worker's

Work on patching interior bldg B & exterior of C, building C, T.I. layout & finish cuting floor, finish rebar mats for interior footings, remove concrete for drains, move material from west parking lot & clean up.

U.I.S Paint - 3 Worker's

Work on painting bldg B exterior & columns & clean up


ESP Excavation - 4 Worker's

Work on power trench & conduit's, work on grading docks, compact, layout & clean up

Horizon Plumbing - 2 Worker's

Work on water lines in building C, layout & clean up



            Weather -  Sunny - High 84  Low 52  






No comments:

Post a Comment

December 13 2022

                                    Daily Job Report Fincon  -  4 Worker's Hang door frames in the west buildout, work on floors in east...