Daily Job Report
Fincon - 18 Worker's
Pour & finish last four dock paving ramps & west approach, work on dock walls, work on hanging man doors on building B, work on mechanical supports in the roof, move material, cut concrete & clean up.
Pour & finish last four dock paving ramps & west approach, work on dock walls, work on hanging man doors on building B, work on mechanical supports in the roof, move material, cut concrete & clean up.
Horizon Plumbing - 2 worker's
Horizon Plumbing - 2 worker's
Work on interior rough in on Bldg C T.I., work on gas lines in building C & clean up
Work on interior rough in on Bldg C T.I., work on gas lines in building C & clean up
ESP Excavation - 3 workers
ESP Excavation - 3 workers
Work on the parking lot, work on sidewalks, compact, layout & clean up
Work on the parking lot, work on sidewalks, compact, layout & clean up
Quicksilver - 12 Worker's
Quicksilver - 12 Worker's
Work on curb & gutter tie in's, set forms, pour & finish water way & clean up
Work on curb & gutter tie in's, set forms, pour & finish water way & clean up
UIS Paint - 2 Worker's
UIS Paint - 2 Worker's
Work on Bldg C & clean up
Work on Bldg C & clean up