Tuesday, September 6, 2022

September 1 2022

                                                       Daily Job Report


Fincon -  12 Worker's

Hang doors in East T.I., work on floors, T.I. layout handrails & set, clean dumpster gates & get ready to prime, grade & clean up.

Highmark Elec - 2 Worker's

Work on bldg B & C interior power & clean up

Capitol Glass - 3 Worker's

Work on the window's in building B, layout & clean up

Horizon Plumbing -  3 worker's

Work on interior rough in on Bldg C T.I., work on gas lines in building B, start underground in West T.I. & clean up

ESP Excavation - 4  workers

Work on grading curb & gutter, work on dock paving, layout & clean up

U.I.S Paint - 2 Worker's

Work on painting bldg B blue stripe north side & clean up

Arbon - 2 Worker's

Work on the dock levlers in building B & C, layout & clean up

            Weather - Sunny - High 98  Low 64

 





























            