Daily Job Report
Fincon - 8 Worker's
Hang doors in East T.I., work on floors, T.I. layout handrails & set, work on dumpster gate priming, pour & finish waterway in dock & clean up.
Hang doors in East T.I., work on floors, T.I. layout handrails & set, work on dumpster gate priming, pour & finish waterway in dock & clean up.
Highmark Elec - 2 Worker's
Highmark Elec - 2 Worker's
Work on bldg B & C interior power & clean up
Work on bldg B & C interior power & clean up
Horizon Plumbing - 3 worker's
Horizon Plumbing - 3 worker's
Work on interior rough in on Bldg C T.I., work on gas lines in building B, start underground in West T.I. & clean up
Work on interior rough in on Bldg C T.I., work on gas lines in building B, start underground in West T.I. & clean up
ESP Excavation - 4 workers
ESP Excavation - 4 workers
Work on grading curb & gutter, work on dock paving, layout & clean up
Work on grading curb & gutter, work on dock paving, layout & clean up
Kimco - 2 Worker's
Kimco - 2 Worker's
Work on fire sprinkler & clean up
Neils Concrete Cutting - 2 Worker's
Work on fire sprinkler & clean up
Neils Concrete Cutting - 2 Worker's
Work on core drilling for handrail & clean up
Work on core drilling for handrail & clean up
UIS Paint - 2 Worker's
UIS Paint - 2 Worker's
Work on interior paint Bldg C & clean up
Work on interior paint Bldg C & clean up
Quality Fire - 2 Worker's
Quality Fire - 2 Worker's
Work on fire alarms & strobes & clean up
Work on fire alarms & strobes & clean up