Wednesday, September 7, 2022

September 7 2022

                                                    Daily Job Report


Fincon -  8 Worker's

Hang doors in East T.I., work on floors, T.I. layout handrails & set, work on dumpster gate priming & clean up.

Highmark Elec - 2 Worker's

Work on bldg B & C interior power & clean up

Capitol Glass - 5 Worker's

Work on the window's in building B, layout & clean up

Horizon Plumbing -  3 worker's

Work on interior rough in on Bldg C T.I., work on gas lines in building B, start underground in West T.I. & clean up

ESP Excavation - 4  workers

Work on grading curb & gutter, work on dock paving, layout & clean up

Kimco - 2 Worker's

Work on fire sprinkler & clean up

Neils Concrete Cutting - 2 Worker's

Work on core drilling for handrail & clean up



            Weather - Sunny - High 103  Low 72