Daily Job Report
Fincon - 18 Worker's
Pour & finish dock paving ramps & south approach, work on dock walls, work on, work on mechanical supports in the roof, move material, cut concrete & clean up.
Pour & finish dock paving ramps & south approach, work on dock walls, work on, work on mechanical supports in the roof, move material, cut concrete & clean up.
Horizon Plumbing - 2 worker's
Horizon Plumbing - 2 worker's
Work on interior rough in on Bldg C T.I., work on gas lines in building C & clean up
Work on interior rough in on Bldg C T.I., work on gas lines in building C & clean up
ESP Excavation - 3 workers
ESP Excavation - 3 workers
Work on the parking lot, work on sidewalks, compact, cut concrete, layout & clean up
Work on the parking lot, work on sidewalks, compact, cut concrete, layout & clean up
Capitol Glass - 2 Worker's
Capitol Glass - 2 Worker's
Work on east building, east wall frames & clean up
Work on east building, east wall frames & clean up
UIS Paint - 2 Worker's
UIS Paint - 2 Worker's
Work on Bldg C east walls & clean up
Work on Bldg C east walls & clean up
PRO HVAC - 2 Worker's
PRO HVAC - 2 Worker's
Work on ductwork in east building T.I. & clean up
Weather - Sunny - High 76 Low 46
Work on ductwork in east building T.I. & clean up
Weather - Sunny - High 76 Low 46