Daily Job Report
Fincon - 4 Worker's
Pour & finish trench drain in the laundry room, work on framing, caulk paving, layout, work on clean outs in the floor, move material & clean up.
Pour & finish trench drain in the laundry room, work on framing, caulk paving, layout, work on clean outs in the floor, move material & clean up.
Capitol Glass - 4 Worker's
Capitol Glass - 4 Worker's
Work on east building, east wall frames & clean up
Work on east building, east wall frames & clean up
UIS Paint - 1 Worker's
UIS Paint - 1 Worker's
Work on Bldg B interior walls & clean up
Work on Bldg B interior walls & clean up
Highmark Electric- 2 Worker's
Highmark Electric- 2 Worker's
Work on power & lights on east t.i. building & clean up
Work on power & lights on east t.i. building & clean up
Pro Heating & Air - 2 Workers
Pro Heating & Air - 2 Workers
Install duct work on east build-out & start on west buildout, fire up wall heaters, unload material & clean up
Install duct work on east build-out & start on west buildout, fire up wall heaters, unload material & clean up
Steerling Structures - 4 Workers
Steerling Structures - 4 Workers
Work on framing in west building T.I., unload material & clean up
Work on framing in west building T.I., unload material & clean up