Friday, November 11, 2022

November 11 2022

                                           Daily Job Report


Fincon -  4 Worker's

Pour & finish trench drain in the laundry room, work on framing, caulk paving, layout, work on clean outs in the floor, move material & clean up.

Capitol Glass - 4 Worker's

Work on east building, east wall frames & clean up

UIS Paint - 1 Worker's

Work on Bldg B interior walls & clean up

Highmark Electric- 2 Worker's

Work on power & lights on east t.i. building & clean up


Pro Heating & Air    -  2 Workers

Install duct work on east build-out & start on west buildout, fire up wall heaters, unload material & clean up

Steerling Structures  -  4 Workers

Work on framing in west building T.I., unload material & clean up


            Weather - Sunny & Cold - High 45  Low 21














No comments:

Post a Comment

December 13 2022

                                    Daily Job Report Fincon  -  4 Worker's Hang door frames in the west buildout, work on floors in east...