Daily Job Report
Fincon - 4 Worker's
Work on framing & backing, bollards, caulk paving, layout, work on cleanouts in the floor, move material & clean up.
Work on framing & backing, bollards, caulk paving, layout, work on cleanouts in the floor, move material & clean up.
Capitol Glass - 4 Worker's
Capitol Glass - 4 Worker's
Work on east building, east wall frames & clean up
Work on east building, east wall frames & clean up
UIS Paint - 2 Worker's
UIS Paint - 2 Worker's
Work on Bldg B interior walls & clean up
Work on Bldg B interior walls & clean up
Highmark Electric- 2 Worker's
Highmark Electric- 2 Worker's
Work on power & lights on east t.i. building & clean up
Work on power & lights on east t.i. building & clean up
Horizon Plumbing - 2 Worker's
Horizon Plumbing - 2 Worker's
Work on plumbing on west T.I. & clean up
Work on plumbing on west T.I. & clean up
Pro Heating & Air - 2 Workers
Pro Heating & Air - 2 Workers
Install duct work on east build-out, work on duct on west T.I. & east T.I., layout unload material & clean up
Install duct work on east build-out, work on duct on west T.I. & east T.I., layout unload material & clean up
Canvis Drywall - 4 Workers
Work on hanging sheetrock from north to south & unload material & clean up
Arbon Equipment - 1 Worker
Work on dock aprons & unload material & clean up
Canvis Drywall - 4 Workers
Work on hanging sheetrock from north to south & unload material & clean up
Arbon Equipment - 1 Worker
Work on dock aprons & unload material & clean up