Monday, November 21, 2022

November 18 2022

                                        Daily Job Report


Fincon -  4 Worker's

Work on framing & backing, bollards, caulk paving, layout, work on cleanouts in the floor, move material & clean up.

Capitol Glass - 4 Worker's

Work on east building, east wall frames & clean up

UIS Paint - 2 Worker's

Work on Bldg B interior walls & clean up

Highmark Electric- 1 Worker

Work on power & lights on east t.i. building & clean up


Pro Heating & Air    -  2 Workers

Install duct work on east build-out, start layout & duct on west T.I.layout unload material & clean up

Canvis Drywall  -  8 Workers

Work on hanging sheetrock from north to south & unload material & clean up

Arbon Equipment  -  2 Worker's

Start layout of dock aprons & unload material & clean up

Rocky Mnt Power - Power to East Building Completed


            Weather - Sunny Cold - High 45  Low 24