Wednesday, November 9, 2022

November 8 2022

                                                 Daily Job Report


Fincon -  4 Worker's

Hang exterior mandoors on building Ccaulk paving, layout, move material, remove concrete for a drain in the laundry room, cut concrete & clean up.

Capitol Glass - 4 Worker's

Work on east building, east wall frames & clean up

UIS Paint - 2 Worker's

Work on Bldg B walls & clean up

Highmark Electric- 2 Worker's

Work on power & lights on east t.i. building & clean up

Horizon Plumbing - 2 Worker's

Work on trench drain in laundry room & air lines on east t.i. building & clean up


Pro Heating & Air    -  2 Workers

Install duct work on both build-outs, work on wall heaters, unload material & clean up

Steerling Structures  -  4 Workers

Start on framing in west building T.I., unload material & clean up


            Weather - Cloudy, Rain, Cold - High 45  Low 32