Daily Job Report
Fincon - 4 Worker's
Work on ceiling drops in the west buildout, work on floors in east buildout, move material & clean up.
Work on ceiling drops in the west buildout, work on floors in east buildout, move material & clean up.
Capitol Glass - 4 Worker's
Capitol Glass - 4 Worker's
Work on the east building, set glass & caulking & clean up
Work on the east building, set glass & caulking & clean up
Pro Heating & Air - 2 Workers
Pro Heating & Air - 2 Workers
Install duct work on east build-out, work on duct on west T.I. & east T.I., layout unload material & clean up
Canvis Drywall - 3 Workers
Work on finishing up sheetrock in east T.I. & unload material & clean up
Install duct work on east build-out, work on duct on west T.I. & east T.I., layout unload material & clean up
Canvis Drywall - 3 Workers
Work on finishing up sheetrock in east T.I. & unload material & clean up
Highmark Elec - 1 Worker
Highmark Elec - 1 Worker
Work on east T.I., work on center buildout on west building & clean up
Work on east T.I., work on center buildout on west building & clean up
Horizon Plumbing - 2 Worker's
Horizon Plumbing - 2 Worker's
Work on plumbing on east buildout, install water heaters and storage tanks, run copper lines & clean up
Work on plumbing on east buildout, install water heaters and storage tanks, run copper lines & clean up
Kimco - 2 Worker's
Kimco - 2 Worker's
Work on fire lines in east T.I. & clean up
Work on fire lines in east T.I. & clean up